Case Studies

Real projects.
Measured results.

HVAC controls and building automation projects with actual energy savings, timelines, and outcomes.

Medical Office200,000 sq ft

Medical Office BAS Upgrade: 200,000 sq ft

Full controls retrofit of a 200,000 sq ft medical office building from proprietary DDC to Niagara N4 with BACnet integration. 32% energy reduction in year one.

32%
Energy Reduction
2.8 years
Payback Period
$182,400
Annual Savings
Commercial Office145,000 sq ft

Proprietary-to-Niagara Migration: Commercial Office

Incremental migration from a locked-in proprietary BAS to open Niagara N4 platform. No downtime, no rip-and-replace.

60%
Service Cost Reduction
99.8%
System Uptime
Single source
Vendors Eliminated
Industrial / Manufacturing310,000 sq ft

Industrial Facility Energy Optimization

Chiller plant and air handling optimization for an industrial facility. Submetering, demand response, and automated sequencing delivered 38% HVAC energy reduction.

38%
HVAC Energy Reduction
$247,000
Annual Savings
210 kW
Peak Demand Reduction

Have a similar project?

Free estimate on any controls, automation, or mechanical service. We'll scope it and explain exactly what you're getting.